Arbitration Initiation

I'd call this extreme.
Hermitage Inn Real Estate Holding Co., LLC v. Extreme Contracting, LLC, 2017 VT 44

If you can say that title five times fast I’ll give you the deed to my house.  Just kidding—I rent. [Pause for laughter] . . . All jokes aside, we have a contract dispute to suss out folks, so let’s get serious.

We see a lot of contract disputes and arbitration clauses around here at SCOV Law (for example, this recent piece from our editor), so I’m not gonna reinvent the wheel.  Hermitage Inn Real Estate Holding Co. hired a firm called Extreme Contracting (yikes!) to do some work on the Hermitage Base Lodge Project.  (Just as an aside, I’ll never make enough money to even set foot on the grounds there, but from the website it looks like a very nice place!)  (Just as another aside—as this piece was being written, news came out that the Hermitage Club is facing bankruptcy, so I might not have a chance to visit there anyway!).  The contract was for $681,987.81.  Not quite up to Dr. Evil’s standards, but still a good amount of cash.


Less than a year after they went into business together, things went south between the two parties, and Hermitage Inn sued Extreme Contracting for breach-of-contract  and brought indemnification claims for liens imposed on the property by Extreme’s unpaid subcontractors.  Since Extreme didn’t have representation at the time the litigation started, the company’s principal filed a pro se answer (and also a counterclaim for $185,000).  The principal claimed that Extreme did not have enough money to hire counsel due to not being paid for the Hermitage job, and asked the court for more time to prepare a defense or, (I love this), “lessons of the law.”

Since trial judges don’t moonlight as law tutors for pro se corporate litigants, the court instructed Extreme’s principal to hire counsel by March 6, 2015, which was extended to April 13 (here’s a good case on the corporate representation rule for anyone who wants to put their law nerd cap on).  Extreme finally got a lawyer in mid-May, well after the deadline, but before the court could rule on Hermitage’s subsequent motions to strike the pro se answer and for default judgment.  Counsel asked for more time to respond to Hermitage’s motions, and that was granted over their objection.

Extreme, now with representation, moved to dismiss the complaint and to enforce the mandatory arbitration clause in the contract both parties signed.  Hermitage of course objected, and demanded default judgment because Extreme’s answer failed to adequately respond to the allegations or provide grounds for their denials, and therefore should be treated as a failure to obey a scheduling order.  Alternatively, Hermitage argued that the case should be stayed pending arbitration, and that Extreme should be responsible for initiating arbitration since they were the ones looking to enforce the mandatory arbitration clause.

The trial court denied Hermitage’s motion for default, and also denied Extreme’s motion to dismiss, and stayed the case pending arbitration, directing Extreme to initiate arbitration by October 1.  Extreme asked for another two weeks, but missed the extended deadline.  Hermitage, yet again, moved for default judgment, and the court gave Extreme one last chance to show that it initiated arbitration.  That didn’t happen, and so the court awarded final judgment to Hermitage by default, and now SCOV gets to weigh in.

SCOV looks first to the arbitration clause at issue here.  It’s not ambiguous, and it was part of the contract that the parties both agreed to, so SCOV looks to its plain language:  “In the event of any dispute hereunder, the matter shall be submitted to and settled by binding arbitration in accordance with the Construction Industry Rules of the American Arbitration Association.”  Both of the parties agree that arbitration was required here, so this part is easy.  What’s disputed is who was required to initiate arbitration.  Hermitage Inn says that they’re fine with arbitration, but by filing suit they waived their right to arbitration, plus Extreme was the party looking to enforce the arbitration clause, so they had the duty to initiate it.  If you think this is a backwards argument, you’re not alone, because SCOV agrees with you.

In addition to the fact that neither Hermitage Inn nor the trial court cited any legal basis for that position, SCOV finds that requiring a defendant in a case to initiate arbitration in a contract dispute defies “basic notions of fairness, and the plain language of the AAA Construction Industry Rules.”  Backed up with a compelling amount of case law, SCOV says that the duty to initiate arbitration rests with the party making the claim for relief, not the respondent.  In this case, this happens to be Hermitage Inn, because they’re the plaintiff!  Therefore, the court never should have ordered Extreme, as the defendant, to initiate arbitration.

With that out of the way SCOV is next asked to decide if the sanction levied against Extreme—the default judgment—was proper.  SCOV comes down with a resounding NO.  First of all, the default was based on an invalid arbitration initiation obligation on the part of Extreme Contracting, the defendant.  SCOV then goes even further and says that even if Extreme had the obligation to initiate arbitration, default judgment still would not have been the proper remedy for the plaintiff.

Hermitage argued that Extreme’s failure to initiate arbitration violated a “scheduling order.”  This is important because under the Vermont Rules of Civil Procedure, a party who violates a scheduling order may be subject to sanctions, including “a judgment of default against the disobedient party.”  SCOV doesn’t buy it.  SCOV doesn’t consider the arbitration order to be a “scheduling order” because there was no pretrial or discovery hearing called for that purpose and therefore doesn’t fit the rule’s plain language.

Next, SCOV is hesitant to approve “litigation-ending” sanctions except for only in the most egregious cases.  This usually involves willful or deliberate disregard for court orders or bad faith.  SCOV doesn’t see that kind of behavior here, so no dice.  Finally, a sanction of default here would have the effect of imposing a litigation-ending sanction on a party who waived their right to arbitration, which is inconsistent with the Federal Arbitration Act.

Hermitage wants SCOV to dispense with Extreme’s arguments regarding the arbitration order and default judgment because they failed to preserve them for appeal.  In spite of Extreme’s history of failing to comply with all kinds of deadlines, and the insufficiency of many of their arguments on motion, SCOV holds that this case should be decided on the merits, and not by default (courts in general strongly prefer settling case on their merits).  SCOV concedes that Extreme missed deadlines throughout the case, however their motion to set aside the default came before final judgment was granted, and therefore should be granted for “good cause.”  SCOV adopts the Second Circuit’s three-part standard to determine whether or not “good cause” exists to vacate the entry of default.  This standard balances (1) “whether the default was willful, (2) whether the moving party has presented a meritorious defense, and (3) whether setting aside the default would prejudice the party who secured the entry of default.”

As to the first factor, there was no finding made about whether or not the default was “willful,” but SCOV doesn’t think it’s necessary to remand this for findings because the other two factors carry greater weight here.  Addressing the third factor, SCOV concludes Hermitage made no showing of prejudice (delay alone or normal litigation expenses don’t count).

As SCOV notes, the main crux of the case involves the second factor, whether the defendant presented a meritorious defense.  This is where things get a little weird.  As SCOV previously stated, Extreme had a meritorious defense to the default judgment.  On the other hand, they never presented an adequate defense to the underlying action, breach-of-contract.  Still, SCOV says that the scales tip in Extreme’s favor, and therefore there was good cause to set aside the default judgment so that this can be decided on the merits.


SCOV vacates the default judgment and remands the case for some extreme arbitration (assuming Hermitage Inn can afford to stay in the litigation).

Comments